TMDP - Monthly  Progress Report of ongoing sub projects(Components A,B &D)- April- 2017
A B (Rs. in crores)
Sl.No. Category Agreement No. & Date Time Period Contract Value Physical Performance upto the month of April 2017 Financial Performance upto the Month of  April  2017
Remarks
Cummilative Progress % Cummilative Payments %
1 2 3 4 5 6 7 8 9 10
1 Assignment - 20
TMDP - Preparation of GIS Base Maps for 37 ULBs of
Telangana
APMDP/Consultancies/2013/18,   dt:16-04-2013 43 months Rs 10.50 Cr out of 11 miletones / 8 milestones completed 72.73% Rs.5.028 Cr 47.78% Final Base Maps and Report awaited
2 Assignment - 33
TMDP - Preparation of GIS Base Maps for 22 ULBs of
Telangana
PD/TMDP/2016-17/7    Dt:27-02-2017 10 months Rs 4.60 Cr out of 11 miletones / 1 milestones completed 9.09% Rs. 0.35 Cr 7.60% The consultant has submitted the inception report
3 Assignment - 22
TMDP -Consultancy Service 'Thrid Party Quality Auditoring and Project Monitoring Consultancy works in 3 ULBs.'
APMDP/Consultancies/2013/22, dt:08-05-2013 3 years Rs 4.75Cr Work is in progress - Rs. 3.95 Cr 83.16% The contract of TPQA is extended from May 2016 to   30-06-2017
4 Assignment - 34
TMDP -Consultancy Service 'Thrid Party Quality Auditoring and Project Monitoring Consultancy works in 5 ULBs.'
PD/TMDP/2017-18/9    Dt:03-05-2017 12 months Rs3.02  Cr Work is progress - - - The contract was concluded on 03-05-2017  